Despite DEP Order To Halt Mariner East 2 Construction, Some Work Allowed

When Danielle Otten woke up Monday morning, she didn’t expect to see men working on the Mariner East 2 pipeline construction site that sits about 40 feet from her backyard, along Devon Drive in Uwchlan Township, Chester County.

For one thing, work in the area had stalled after drilling dried up and damaged nearby water wells this past summer. And just last week, the Pennsylvania Department of Environmental Protection issued a court order haltingconstruction along the 350-mile long pipeline after Sunoco/Energy Transfer Partners continued to violate its permits, causing damage to private water wells, streams and wetlands.